Wednesday, 14 August 2013

The End of Loadshedding in Nepal

The Power shortage of Nepal is one of a major problem.  20hrs of load shedding was recorded in Nepal . It's been almost a decade that the country is suffering a heavy power shortage problem. The rate of   growth of electricity is near to 10% as by the NEA report in july 2012 .
Total installed capacity of electric power in Nepal is around 748 MW as of 2013. But  maximum demand is about 1026.6 MW(2012 NEA report). There is a total gap of more then 300MW in general .  Major crisis is in the spring and winter seasons where production of Hydropower plant even fall to the more  minimum level upto 500MW because most of  plant are run off river type.
Still it shows of 50% percent of power is shortage in the maximum peak demand in drought seasons.
     How we can decrease this much of gap?  Well big Hydropower is a time consuming project and it will take more then 4yrs  for the completion , in the case of Nepal. These  are  major  projects

Name of the Project                                Installed capacity    Project started time         Ending  time
1) Upper Tamakoshi project                        (456MW)               May 18 2011                      5yrs (extended upto 2015)
2) Kulekhani III Hydropower Project          (14MW)                April 27, 2008               December 14, 2014
3) Chameliya Hydro Electric Project           (30MW)                   2007                                 2013( extended to March 2015)
4) Rahughat Hydro Electric Project              (32MW)                2010/11                            2016
5) Upper Trishuli 3A Hydro Electric Project  (60MW)            1st June 2011                  35 months(not completed)      
6) West Seti Hydropower Project                  (750MW)                 -                                       -
                       Total  Under construction =   ( 1342MW )

Lets imagine that the whole project  will be complete by  year 2021 then  data shows that  in 2021 maximum demand will be rise of  about 1000 MW, which again  installed capacity will be  less then demand capacity. So it is  not easy to say that Nepal load-shedding problem  will be completely end by the 2021 but I am  pretty sure that if megha project will not come to exist and new more project will not be added then  load shedding will remains as it is  for one more decade.